Installation of Additional A Post Pillar Before undertaking this work ensure you have all the necessary resources to complete the task; - 1 Only use tube provided
by Bowler Off Road Ltd. Substitution with other tube will 2 A welder who is
competent in welding tube in a confined area must carry out the welding.
3 Before attempting
to weld the tube ensure the powder coating is removed down to bare |
|||||
![]() |
|||||
Instruction 10 Complete section 'B' on page 7 of the new Rollcage Certificate to comply with FIA regulations. Replace
the old certificate with the new certificate and keep it with the rest
of the car paperwork as you will need it to pass the technical checks. |
|
||||
![]() |